Renovation Timeline: Key Collection to Move-In

Most renovation stress comes from timeline surprises, not costs. Here's a realistic week-by-week map from key collection to move-in for a typical flat.

Before key collection (T-12 to T-4 weeks)

Engage your designer 2–3 months early. Use this runway for space planning, material selection and quotation. Popular firms book out 4–8 weeks ahead — waiting until keys are in hand adds a month to everything.

Weeks 1–2: Approvals and protection

HDB permit or MCST approval submission, hoarding and floor protection, then hacking. Permits take 1–2 weeks; nothing noisy happens without them.

Weeks 2–4: Wet works and rough-ins

Masonry, tiling, waterproofing, plus electrical and plumbing rough-ins. This sequence is hard to reverse — confirm your electrical point layout before this stage, not after.

Weeks 3–7: Carpentry fabrication

Carpentry is built off-site in parallel (3–5 weeks). This is the schedule's long pole; late design changes here cause the classic two-week slip.

Weeks 7–9: Installation and finishing

Carpentry installation, painting, light fittings, glass and doors. Then deep cleaning and your defects walkthrough — document everything before the final payment.

Buffer honestly

Quoted 8 weeks usually means 10 in practice. Material shipping delays and rectification rounds are normal; plan your lease-end or move date with a 2-week cushion.

Starting your journey? Get matched free with firms whose schedules fit your key collection date.

Ready to bring this to life?

Get matched with interior design firms that specialise in exactly this — free.

Try Get Matched for Free